145MW Romanian Solar Power Project

The Solar PV Park project is planned in Alges, Romania. The project is currently in the licensing phase. Currently in development. After construction is complete, the project is expected to be commissioned in 2022.

After 2 months of follow-up by the salesman, KUKA CABLE participated in the project as a cable procurer and will operate and maintain the solar photovoltaic power generation project. The cables required for this project are as follows:

Solar Cable, 6 mm2, 1500 V, H1Z2Z2-K————93000M

ALPVC, 4x240 mm2, 0,6/1 kV, YAVV-NAYY————122100M

ALXLPE, 95/16 mm², 20,3/35 kV, NA2XS(F)2Y————122100M

ALXLPE, 150/25 mm², 20,3/35 kV, NA2XS(F)2Y————3360M

ALXLPE, 240/25 mm², 20,3/35 kV, NA2XS(F)2Y————18900M

ALXLPE, 630/35 mm², 20,3/35 kV, NA2XS(F)2Y————17800M

Grounding Cable, 1 x 16 mm2, NYY-J————19000M

Communication Cable, RS485/ 8x2x0.5, Li2YCYv (TP)——200M

Communication Cable, Fiber Optic Cable, A-DQ(ZN)B2Y, 1x12, G50/125 max., 2500 N——16000M